The Connecticut Department of Transportation’s office of Engineering is implementing a Pavement Preservation Project for the 2025 construction season. A section of I-91 in the Town of East Windsor and Enfield has been identified as a candidate for this program.

The department is developing plans to mill and overlay a section of I-91 from Route 140 (Bridge Street) overpass to the Massachusetts State Line for a total distance of approximately 7.3 miles. This project will also include milling and overlaying of the on-ramps and off-ramps. Detour routes will be provided should ramps need to be closed for construction activities.

The present schedule indicates that the design will be completed in 2024, with construction anticipated to start in Spring 2025.